Yandi Project

Yandi_3 Yandi-cropped
Yandi_2 Yandi_1

Yandi Project Design included mechanical design, control design, commissioning, and chute designs(2).

Year Built: 2003
Location: Yandi Ore handling – Pibara, Australia
Conveyor Length: 5.1 km
Power: 2,250 kW
Tonnage: 4,000 tph
Belt Strength:  ST-1900 N/mm
Belt Speed:  5.5 m/s
Material Conveyed: Iron Ore
Interesting features:
–   Feed chute design for Voest-Alpine.

Chute Design

Project scope included chute design and DEM analysis for two chutes on a system conveying iron ore, each with capacity up to 2,000 tph.
Number of Chutes: 2
Chute Design: Yes
ROCKY DEM Analysis: Yes
Capacity:  2,000 tph


Yandi Project was last modified: May 4th, 2016 by CDI